If D = duration, EF = earliest finish time, ES = earliest start time, LF = latest finish time, LS = latest start time, which relationship does not hold?

Industrial Engineering Mcqs

A.EF = D – ES
B.EF = D + ES
C.LF = LS + D
D.None of the above